Mitigation Milestone Reached at Mattawoman Creek Mitigation Site

Photo courtesy of GreenVest

Mattawoman Creek Mitigation Project will Restore and Protect 80+ Acres of Mattawoman Creek, Chesapeake Bay’s Most Productive Tributary

As one of the Chesapeake Bay’s most productive tributaries and a vital part of Maryland’s natural resources, Mattawoman Creek supports some of the largest populations of finfish, amphibians, and birds in the state. A collaborative team of private and public sector entities have designed the “Mattawoman Creek Mitigation Site” in Pomfret, Charles County, Maryland, an effort that will enhance or create 64+ acres of wetlands and restore nearly 3,800 linear feet of this perennial stream.  With over 28,500 native trees and shrubs to be planted, this mitigation project will result in 80+ acres of continuous, forested wetland with complex and diverse vegetative communities. It is expected to provide a wide array of habitat to resident and transient wildlife, including birds, reptiles, invertebrates, amphibians and rare, threatened and endangered species.

Unique to this project, Mattawoman Creek Mitigation Site is Maryland’s first-ever Umbrella Mitigation Banking Instrument (UMBI) for federal and other government agency use.   A UMBI is the bundling of multiple mitigation banks into one agreement in order to streamline the regulatory approval process, thereby eliminating steps and involving fewer resources. The Maryland UMBI document helps the USAF and other public agencies secure certainty of cost and schedule, facilitate timely permit issuance, and expedite the satisfaction of their permitted requirements for planned capital improvement projects. This approach also maximizes the scale of restoration and resulting land protection and efforts, creating contiguous blocks of habitat with greatly enhanced benefits compared to single, permittee-responsible projects. This precedent was a result of a partnership between United States Air Force (USAF) and Joint Base Andrews (JBA), U.S. Army Corps of Engineers (USACE), Maryland Department of the Environment (MDE), GreenTrust Alliance, GreenVest, and Princeton Hydro.

Projects completed under the UMBI will reduce federal and state workload expediting the regulatory review and issuance of permits by the MDE and USACE. Additionally, projects completed under this UMBI will aid in compliance with the Federal Paperwork Reduction Act where federal regulatory staff can evaluate success and performance issues for multiple permittees at one single habitat restoration or mitigation site. In addition, federal costs are capped, and liabilities  are transferred through to GreenVest, the private sector operator, and GreenTrust Alliance, the nonprofit bank sponsor, who will also serve as the long-term steward of sites restored under this program.

Pictured is the southern restoration area after
sorghum germination, prior to wetland creation
and reestablishment.
A function-based stream assessment was
performed on the degraded channel.

 

Photo courtesy of GreenVestDesign, engineering/modeling, and permitting of the site was completed by  Princeton Hydro and GreenVest under our currently Ecosystem Restoration contract with the USACE. Princeton Hydro also provided an Environmental Assessment and Environmental Baseline Survey, and conducted a geotechnical investigation, which included the advancement of test pits, visual and manual investigation techniques and logging, infiltration testing, laboratory soils testing, and seasonal high-water table estimations.

A wetland water budget was also developed for the proposed wetland creation and restoration to determine if sufficient water is available to establish or reestablish wetlands on the site. It was also used to inform design development including proposed grading and plant community composition. The establishment and re-establishment of wetlands on the site will be accomplished through directed grading, ditch plugging and stream restoration designed to maximize the retention of surface water, floodplain re-connection, and groundwater inputs.

Highlights from the Mattawoman Creek Wetland and Stream Mitigation project:
  • 80 acres of land were placed into conservation easement and removed from active row crop production and cattle pasture. The easement, which is held by GreenTrust Alliance, provides permanent protection for all 80 acres.
  • Over 64 acres of wetlands will be restored, created, enhanced or preserved, which will sequester approximately 75 tons of carbon per year.
  • 3,798 linear feet of perennial stream will be restored by re-establishing, historic floodplain access during more frequent storm events, stabilizing hydraulics and geomorphology, and adding aquatic habitat value.
  • Full integration of the wetland and stream restoration elements will occur exponentially, increasing anticipated functions and values in the post construction condition. Functions include: storm damage and flood attenuation, groundwater recharge and discharge, nutrient cycling and sequestration, local water quality improvement, and wildlife habitat enhancements.
  • This project will also create and enhance the forested wetland and stream habitat for the State-listed Threatened Selys’ Sundragon (Helocordulia selysii).
  • As part of the site design, over 28,500 native trees and shrubs will be planted.
  • The Mattawoman Creek Mitigation Site is located within a Tier 3 Biodiversity Conservation Network area. These areas are classified by the Department of Natural Resources as “highly significant for biodiversity conservation” and are priority conservation areas that support critical species and habitats.
  • The project will yield advanced mitigation values: 7.913 in wetland credits and 1,595 in stream credits. These credits are durable and will be available for JBA’s use in order to satisfy permitted impacts associated with planned capital improvement projects.

Over 6,000 acres (25%) of the Mattawoman Creek watershed has been protected by public ownership and various conservation and agricultural easements, which, in addition to the Mattawoman Creek Mitigation Site, help ensure that Mattawoman Creek forever remains a high-quality destination for outdoor recreation.

Princeton Hydro specializes in the planning, design, permitting, implementing, and maintenance of tidal and freshwater wetland rehabilitation projects. To learn more about our wetland restoration, creation, and enhancement services, visit: http://bit.ly/PHwetland

October Events Spotlight: Conferences, Workshops & Galas

Throughout October, Princeton Hydro is proud to participate in a number of conferences and events on topics ranging from floodplain management to ecological restoration to dam removal:

October 10: Society for American Military Engineers (SAME) MEGA Maryland Small Business Conference

The conference, being held in Baltimore, gives small and minority businesses in the architecture, engineering and construction industries the opportunity to come together with federal agencies in order to showcase best practices and highlight future opportunities to work in the federal market. The program consists of networking events, a variety of speakers and small business exhibits. Be sure to stop by the Princeton Hydro booth to say hello to President Geoffrey Goll, P.E. and Communications Strategist Dana Patterson.

LEARN MORE & REGISTER

 

October 11: Great Swamp Gala & Silent Auction

The Great Swamp Watershed Association, a nonprofit organization dedicated to protecting and improving the water resources of the Passaic River region, is hosting its 2018 Gala & Silent Auction. This year’s event is being, held in honor of former New Jersey Governor Thomas Kean, for his environmental leadership during his administration for enacting landmark protections for New Jersey’s shoreline and freshwater wetlands. present and future generations. The evening will include a cocktail hour, dinner banquet, expansive silent auction, and remarks delivered by Governor Kean. Princeton Hydro is proud to be a Benefactor of the event and looking forward to attending.

LEARN MORE & REGISTER

 

October 11 – 13: Atlantic Estuarine Research Society (AERS) Fall Meeting

The theme of this year’s AERS Fall Meeting is “The power of framing your message: It’s not what you say, it’s how you say it!” Participants will gather at Stockton University to hear a variety of ignite-style presentations about misconceptions that typically surround scientific work, how to address them, and how to re-frame your message to be better understood by the general public and other non-scientists and increase stakeholder involvement. Princeton Hydro’s Senior Aquatics Scientist Jack Szczepanski, PhD will be attending the conference; chat with him to learn more about our pond and lake services.

LEARN MORE

 

October 11 – 13: Society for Ecological Restoration (SER) New England 2018 Regional Conference

This year’s SER New England conference brings together stewards, researchers, students, regulators, community activists and practitioners to explore innovative ecological restoration techniques and projects that connect communities within and across ecosystems. The conference includes a variety of plenary talks, field trips, workshops and a keynote address, which will be given by Stewart Diemont of SUNY College of Environmental Science and Forestry. The keynote, titled “Learning from the People and the Land: Traditional Ecological Knowledge Toward Restoration of Ecosystems and of our Connection with Nature,” is free and open to the public.

Members of the Princeton Hydro are attending the conference and leading two sessions: Laura Wildman, Water Resources and Fisheries Engineer, is leading a workshop about implementing dam removal to restore rivers. Paul Woodworth, Fluvial Geomorphologist, is presenting on the post-dam removal monitoring of active and passive restoration approaches utilizing the Hyde Pond Dam removal as a tangible example.

LEARN MORE & REGISTER

 

October 11: Hudson-Delaware Chapter of the Society of Environmental Toxicology and Chemistry (HDC-SETAC) 2018 Fall Workshop

HDC-SETAC is a professional society for scientists, engineers and related disciplines concerned with environmental science and health throughout the Hudson River and Delaware River metropolitan area. The 2018 Fall Workshop, being held at Villanova University, aims to enhance participants’ knowledge of “Harmful Algal Blooms and other Emerging Contaminants.” Princeton Hydro’s Director of Aquatic Programs Dr. Fred Lubnow is giving a presentation on “The Monitoring and Management of Cyanotoxins in Raw Water Supplies.” We hope to see you there! 

LEARN MORE

 

October 12: Association of New Jersey Environmental Commissions (ANJEC) 2018 Environmental Congress

ANJEC, a nonprofit organization supporting efforts to protect the environment and preserve natural resources in communities throughout New Jersey, is hosting its 45th Annual Environmental Congress at Mercer County College. The Environmental Congress is an annual statewide gathering of environmental commissions, local officials, agencies, citizen groups and environmental organizations, which includes an exhibitors hall, farmer’s market, and workshops on a variety of current environmental topics. Princeton Hydro, a business member of the ANJEC, will be exhibiting during the event. Stop by the booth to say hello to Dr. Stephen J. Souza, Princeton Hydro Founder and ANJEC Board of Trustees member, and Dana Patterson, Communications Strategist for Princeton Hydro.

LEARN MORE & REGISTER

 

October 23 – 25: New Jersey Association for Floodplain Management (NJAFM) 14th Annual Conference

NJAFM is hosting its 14th Annual Conference and Exhibition in Atlantic City, NJ. Participants will attend meetings and seminars covering topics, including hazard mitigation, flood insurance, infrastructure, mapping, planning, flood modeling, regulations, floodproofing, stormwater management, flood proofing, construction standards and more. Princeton Hydro’s Christiana Pollack, GISP, CFM and NJDEP’s Jessica Jahre, PP, AICP, CFM are giving a presentation, titled “A Flood Assessment for the Future,” for which they’ll showcase a flood assessment and flood mitigation analysis that Princeton Hydro performed in the Lower Moodna Creek Watershed.

LEARN MORE & REGISTER

 

October 23: “Undamming the Hudson River” Film Screening and Panel Event, Free & Open the Public

Riverkeeper and Patagonia present the premiere of “Undamming the Hudson River,” a short documentary film by National Geographic filmmaker Jon Bowermaster showcasing Riverkeeper’s efforts to restore natural habitat by eliminating obsolete dams throughout the Hudson River Estuary. The screening will be followed by refreshments and a panel discussion, moderated by Bowermaster, featuring experts in the field and an audience Q&A. Panelists, include:

  • Laura Wildman, PE – Water Resources and Fisheries Engineer, Princeton Hydro
  • George Jackman – Habitat Restoration Manager, Riverkeeper
  • Gwen McDonald – Director of Green Projects, Save the Sound
  • Andy J. Danylchuk, PhD – Associate Professor of Fish Conservation, UMASS Amherst, and Patagonia Fly Fishing Ambassador

This event is free and open to the public and will take place at Patagonia SoHo, 72 Greene St, New York, NY 10012 from 7:30 – 10pm.

RSVP HERE

 

October 24: Mid-Atlantic Chapter of the Urban & Regional Information Systems Association (MAC URISA) 2018 Conference

MAC URISA 2018, the largest GIS conference in the Mid-Atlantic region, will showcase outstanding and innovative uses of GIS technologies in the area. The program includes a variety of presentations, breakout sessions, a GIS Techspo forum, lightening talks, and more. Thomas Hopper, Princeton Hydro’s GIS Analyst, is providing a technical demonstration on the Linkage Mapper GIS Toolkit, which was created by the Nature Conservancy to support habitat connectivity analyses.

LEARN MORE & REGISTER HERE

 

October 30 – November 2: North American Lake Management Society (NALMS) Conference

NALMS is hosting its 38th International Symposium in Cincinnati Ohio, titled “Now Trending: Innovations in Lake Management.” This year’s symposium includes a robust exhibit hall, a variety of field trips, and a wide array of presentations on topics ranging from the latest in monitoring technologies to combating invasive species to nutrient and water quality management and more. Princeton Hydro’s Dr. Fred Lubnow, Director of Aquatic Programs, and Dr. Stephen Souza, Founder, both of whom have been members of NALMS since its inception, are presenting and exhibiting during the conference.

LEARN MORE

 

October 31 – November 2: Society for American Military Engineers (SAME) Small Business Conference (SBC)

SAME gives leaders from the A/E/C, environmental, and facility management industries the opportunity to come together with federal agencies in order to showcase best practices and highlight future opportunities for small businesses to work in the federal market. Princeton Hydro is proud to be attending the 2018 SAME SBC Conference, which is being held in New Orleans and co-locating with the Department of Veteran’s Affairs’ National Veterans Small Business Engagement. The program consists of networking events, small business exhibits, a variety of speakers and much more.

LEARN MORE & REGISTER

 

STAY TUNED FOR OUR NOVEMBER EVENT SPOTLIGHT!

Dam Removal Underway in Watertown, Connecticut

Deconstruction of the Heminway Pond Dam, Watertown, CT on July 16, 2018.

As dams age and decay, they can become public safety hazards, presenting a failure risk and flooding danger. According to American Rivers, “more than 90,000 dams in the country are no longer serving the purpose that they were built to provide decades or centuries ago.” Dam removal has increasingly become the best option for property owners who can no longer afford the rising cost of maintenance and repair work required to maintain these complex structures.

Dams can also cause environmental issues such as blocking the movement of fish and other aquatic species, inundating river habitat, impairing water quality, and altering the flow necessary to sustain river life. Removing nonfunctional, outdated dams can bring a river back to its natural state and significantly increase biodiversity for the surrounding watershed.

A view from the site of the Heminway Pond Dam removal on July 19, 2018.

Currently, work is underway in Watertown, Connecticut to remove the Heminway Pond Dam, which restricts fish passage in Steele Brook, creates a pond with increased water temperatures and high bacterial levels due to high geese populations, and encourages deposition of iron precipitate in the stream channel just downstream of the dam.

Princeton Hydro designed the engineering plans, managed permitting and is now overseeing construction for the removal project. The removal of the Heminway Pond Dam is identified as an integral component in addressing water quality impairment between the dam and Echo Lake Road.

CT DEEP recently published this piece encapsulating the Heminway Pond Dam removal project:

REMOVAL OF HEMINWAY POND DAM ON STEELE BROOK IN WATERTOWN UNDERWAY

Upstream at rock-filled breach in Heminway Pond Dam and shallow, dewatered impoundment on Steele Brook in Watertown (7-18-18)

After almost 15 years of discussion and planning with the Town of Watertown and other partners, removal of Heminway Pond Dam on Steele Brook in Watertown finally got underway in early July.  Though no longer functional, the dam and pond were originally constructed to supply water for a former thread/string mill.  The Town acquired the dam and pond from the Siemon Company, the most recent owner, in 2007 with an eye towards removing the dam, restoring the river and converting the dewatered impoundment area into a passive recreation area, including an extension of the Steele Brook Greenway.  With these goals in mind, the Town approached CT DEEP for help with removal of the dam.

As it turns out, CT DEEP, has also had a strong interest in seeing this dam removed.  It is anticipated that dam removal will improve the hydrology in this section of Steele Brook and eliminate a water quality impairment which manifests itself during hot weather and low flow conditions, as an orange-colored plume of water (due to iron precipitate) immediately downstream of the dam that impacts aquatic life.  Dam removal would also benefit fisheries by restoring stream connectivity and habitat.

Working towards these mutual goals, CT DEEP was able to provide federal CWA 319 nonpoint source grant funding to USDA NRCS to develop a watershed-based plan for Steele Brook to address nonpoint source impairments that includes a dam removal feasibility analysis for Heminway Pond Dam.  Based on the recommendations in this plan, CT DEEP subsequently provided additional 319 grant funds to the Town of Watertown to hire a consultant to develop a dam removal design package, and assist with permitting and preparation.

With the Town of Watertown as a strong and vested partner, CT DEEP is now helping this project over the finish line by providing a combination of 319 and SEP funds to accomplish the actual dam removal and restoration of Steele Brook.  Dayton Construction Company is performing the construction and Princeton Hydro is the consultant overseeing the project on behalf of the Town.  The Northwest Conservation District is also assisting with the project.  It is anticipated that the majority of the work will be completed by this Fall.  U.S. EPA, ACOE and CT DEEP have all played active roles with regard to permitting the project.

 

A view of the first notch during the Heminway Pond Dam removal on July 17, 2018.

Princeton Hydro has designed, permitted, and overseen the reconstruction, repair, and removal of dozens of small and large dams in the Northeast. Click here to read about a recent dam removal project the firm completed on the Moosup River. And, to learn more about our dam and barrier engineering services, visit: bit.ly/DamBarrier.

Creative, Timely Solutions Lead to Successful Dam Repair in Medford Lakes

By Kevin Yezdimer, P.E. and Jim Hunt, P.E.

Just 25 miles east of Philadelphia, on the edge of the New Jersey Pinelands region, sits a network of 22 lakes that serve a multitude of recreation purposes for the residents of Medford Lakes. Serving as the guardian to these natural beauties is the Medford Lakes Colony (MLC), a private homeowner association. Homeowners in this community contribute to a “Lake Restoration Fund,” managed by MLC, which is used to maintain the water control structures and monitor the water quality for the bodies of water within the community. This dedicated fund is often used for dredging of the lake beds; repairs and replacement of dams, spillways, and culverts; installation of aerators or fountains to promote long-term benefits to water quality; treatments for weeds and algae; and the maintenance of the coves and beaches.

In mid-April, a concerning blockage developed in Lake Wauwauskashe Dam’s spillway and water was backing up at the upstream outlet structure. The 30-inch wide corrugated metal pipe serves as the dam’s primary (and only) outlet under Wagush Trail, a neighborhood road connecting Lake Wauwauskashe and Lake Mushkodasa. During the attempt to clear the mass of accumulated woody-debris via vacuum truck extraction, a previous repair consisting of a 5’ segment of corrugated plastic pipe had been dislodged and expelled from the downstream end of the spillway. With a compromised dam and flooding in the forecast, MLC acted immediately to handle this emergency dam repair.

Primary Spillway Inlet
Before – Upper portion of the existing corrugated metal pipe was collapsed. After – Pipe was slip-lined and the annulary space was grouted.

 

Given Princeton Hydro’s long-term history of inspecting and maintaining dams and levees in Medford Lakes, MLC contracted our experts to assist. The next day, our team of geotechnical engineers were on-site to investigate the situation. To facilitate the inspection and minimize the stress/pressure on the dam, the upstream and downstream lakes were lowered via an NJDEP Fish and Wildlife Lake Lowering Permit. Additionally, a video inspection of the compromised culvert pipe was conducted. Our geotechnical team observed that the upstream portion of the pipe had collapsed and the structure was experiencing significant seepage (i.e. water flowing through undesirable paths through the dam with the potential for soil piping and stability failure).

Primary Spillway outlet
Before – The existing corrugated metal pipe had corroded and erosion had taken place around the outlet. After – Pipe has been slip-lined and outlet protection (riprap) was installed to stabilize the surrounding soil.

 

With the risk of potential dam failure, Princeton Hydro immediately kicked-off coordination with the NJDEP Bureau of Dam Safety, NJDEP Division of Land Use Regulation, the Pinelands Commission, and the Borough of Medford Lakes. Our licensed engineers promptly developed the repair concept and associated scope of work, detailing our proposed means and methods for the emergency repair.

“We take the potential risk of dam failure very seriously, as safety is one of our core values,” said Kevin Yezdimer, P.E. Director of Geosciences Engineering at Princeton Hydro. “Our geotechnical team prioritized the design, permitting, and implementation of this emergency repair to assure the safety of our client and the community.”

Injection grouting underway (Grout pressure is monitored during placement & the ground surface is monitored for signs of heave).

This included addressing the collapsed pipe; utilizing cementitious injection grouting and compaction grouting to eliminate seepage pathways and stabilize the earthen dam in-place; and provide spillway outfall protection. Through private solicitation, Princeton Hydro selected Compaction Grouting Services, Inc. as the specialty contractor to perform the repair.

A considerable volume of water was required to prepare the grout mixes, and no water sources were available adjacent to the project site. Seeking out solutions, MLC proposed the unique idea of using reclaimed wastewater from the local wastewater treatment plant. Our team confirmed that reuse of the reclaimed wastewater was indeed within the guidelines of the “Technical  Manual for Reclaimed Water for Beneficial Reuse,” and we successfully facilitated approval to use it with NJDEP Division of Water Quality.

Placement of cellular fill into the hollow concrete structure is underway. A lightweight foaming agent was added to the grout mix within the concrete truck. The lightweight grout was then pumped into the structure.

As the construction effort ramped-up, some complications arose. By design, this unique structure allows water flow over the dam’s weirs and drops 8 to 10 feet vertically before travelling under the roadway through the primary spillway. Above the primary spillway is a concrete structure that spans from the upstream lake to the downstream lake and immediately beneath the local roadway. It was discovered that this 50’ long, 6’ deep, concrete structure was hollow and served as a potential seepage pathway. Princeton Hydro proposed to fill-in the hollow structure with a lightweight cellular fill material in order to cut-off the potential seepage pathways, eliminate the 6’ deep hollow chamber beneath the roadway, and facilitate a long-term repair solution.

Implementation of this strategy was further complicated when a utility markout and a subsequent video inspection of the hollow structure confirmed that a gas line passed through the structure on the downstream side of the roadway. Princeton Hydro coordinated with South Jersey Gas to disconnect the gas line in order to minimize risk during construction and eliminate future complications. The neighborhoods on either side of the dam were fed redundantly, so their service was not interrupted during this process.

Overall, the emergency dam repair solution involved an in-situ soil stabilization of an earthen embankment dam via compaction/injection grouting, slip-lining the primary spillway, stabilization of the downstream outlet, and utilization of reclaimed wastewater as a water source for on-site grout batching. The following was completed by our team and contractors during the course of the emergency construction:

  • Slip-lining of the failed 30-inch pipe using a smooth, slightly smaller in diameter high density polyethylene pipe (HDPE) pipe inside of the existing pipe, providing an equal or greater hydraulic capacity as that existing;

  • Grouting of the annular space between the new and old pipes;

  • Non-woven geotextile fabric and riprap outfall protection were placed around the downstream outlet of the culvert pipe to provide scour protection;

  • Compaction and injection grouting was performed in multiple locations. The compaction grout utilized a “low-slump” mix while the injection grout utilized a much more mobile or fluid mix allowing for filling of existing seepage pathways or soil voids, and;

  • Approximately 44 cubic yards of lightweight cellular-grout backfill was utilized to fill in the hollow concrete structure beneath the roadway completing the emergency repair without the need for complete outlet structure or earthen dam reconstruction.

Lowering New Pipe Into Place

Creative, innovative solutions paired with timely coordination and expertise drove the success of the Lake Wauwauskashe Dam emergency repair.

Princeton Hydro has designed, permitted, and overseen the reconstruction, repair, and removal of a dozens of small and large dams in the Northeast. To learn more about our dam and barrier engineering services, visit: bit.ly/DamBarrier.

Kevin M. Yezdimer, P.E., Princeton Hydro’s Geoscience Engineering Director, is a multidisciplinary professional civil engineer who holds degrees in both Geology and Civil Engineering, and has 11 years of progressive and varied work experience as both a design consultant and project owner with Geotechnical & Construction Engineering being his core area of expertise. He has significant experience performing soil and rock core sampling programs, infiltration testing, soils laboratory testing, foundation design (shallow and deep), preparation of construction recommendations,  and overseeing construction review activities (e.g., earthwork, foundations, concrete, masonry, structural steel, roadway, and utility construction).

 

Jim Hunt, P.E., joined Princeton Hydro in 2017 as a Geotechnical Engineer and provides a wide range of engineering services for the firm including: subsurface explorations, bearing capacity and settlement analyses, slope stability analysis, stability analysis of existing structures, preparation of technical deliverables, and cost estimating.

 

 

 

Wild & Scenic Film Festival is Coming to Hackettstown

To celebrate the 50th Anniversary of the Wild and Scenic Rivers Act, the Musconetcong Watershed Association (MWA) is hosting the “Wild & Scenic Film Festival On Tour”. The festival is free and open to the public, but seating is limited so, registration is required. The festival will be held on Sunday, September 9th from 10 am to 2 pm at Centenary University in Hackettstown, NJ.

To bring communities together around local and global environmental issues, The “Wild & Scenic Film Festival” goes “on-tour” partnering with nonprofit organizations and local groups to screen films year-round with hopes of inspiring individuals to take environmental action. The tour stops in 170 communities around the globe, features over 150 award-winning films, and welcomes over 100 guest speakers, celebrities, and activists who bring a human face to the environmental movement.

Credit: NPS.gov

The Hackettstown, NJ tour event will feature 11 short films including River Connections, which celebrates the 50th anniversary of the Federal Wild and Scenic Rivers Act, under which the Musconetcong River is protected. The film explores the importance of free-flowing rivers and highlights the recent Hughesville Dam removal project. An interactive panel event will follow the film screening and feature experts including MWA Executive Director Alan Hunt, Ph.D. and Princeton Hydro President Geoffrey Goll, P.E., who were both interviewed in the film.

“Our multidisciplinary approach to dam removal using ecology and engineering, paired with a dynamic stakeholder partnership, led to a successful river restoration, where native fish populations returned within a year,” said Princeton Hydro’s President Geoffrey Goll, P.E. “We are grateful for MWA’s hard work in organizing this film festival so we can continue to share our dam removal success stories and the importance of the Wild and Scenic Rivers Act.”

Princeton Hydro, a proud sponsor of the “Wild & Scenic Film Festival On Tour,” has worked with MWA to design five dam removals on the Musconetcong River, including the Hughesville Dam. As noted in the River Connections film, the Hughesville Dam was a major milestone in restoring migratory fish passage along the Musconetcong. Only a year after the completion of the dam removal, American shad were documented as having returned to the “Musky” for the first time in 250 years.

The tour leads up to the annual 5-day film festival, which will be held January 17-21, 2019 in Nevada City and Grass Valley, California. Sponsored by National Park Service, the Wild & Scenic Film Festival honors the Wild and Scenic Rivers Act, landmark legislation passed by Congress in October 1968 that safeguards the free-flowing character of rivers by precluding them from being dammed, while allowing the public to enjoy them. It encourages river management and promotes public participation in protecting streams.

EVENT DETAILS:

Date:         Sunday, September 9th

Time:         Doors open at 10 am and shows start at 11 am

Location:  Centenary University, Sitnik Theatre,
                  400 Jefferson St, Hackettstown, NJ 07840

Tickets:     FREE! Please register in advance:
                   https://goo.gl/NrwcgE

 

Interested to learn more about River Connections?
Check out our blog celebrating the release of the film: 

UPDATE: The Columbia Dam Is Coming Down

It’s happening! The Columbia Dam on the Paulins Kill in Northern New Jersey is finally coming down thanks to a successful collaboration between The Nature Conservancy, American Rivers, U.S. Fish and Wildlife Service, NJDEP Division of Fish and Wildlife Service, and Princeton Hydro. The first cut on the main dam wall was made just two weeks ago, and the water has started flowing downstream as the concrete is slowly being removed by the contractors RiverLogic Solutions and SumCo Eco-Contracting.

“In New Jersey, successful dam removal projects are often the result of partnerships between nonprofit organizations, federal and state agencies, consultants, and others working together toward the common goal of river restoration,” exclaimed Dr. Laura Craig, Director of River Restoration, American Rivers. “The first day of dam demolition is always a joyous occasion for project partners, but I was especially happy to see the river flowing through the breached Columbia Dam for the first time after working so intensely on this project for the last few years.”

Princeton Hydro has been involved with the engineering and restoration design from the beginning, so we’re very excited to report on this major update.  Our team of engineers and ecologists studied the feasibility of removal as requested by American Rivers in partnership with the New Jersey chapter of The Nature Conservancy.  We investigated, designed, and prepared the necessary permits for the removal of this dam. And, now we’ve been subsequently been hired to provide construction administration services during the removal process, which means we get to see the dam come down firsthand, piece by piece!

“It is truly amazing and exciting to finally see the main and remnant dams come down, as I have been involved in this restoration effort since the feasibility stage,” said Kelly Klein, Senior Project Manager, Princeton Hydro. “I am so honored to be part of this dynamic team and to collaborate with our project partners during every stage of this dam removal.”

Geoff Goll, Princeton Hydro and Beth Styler Barry, The Nature Conservancy on site August 3, 2018. Photo credit: Laura Craig, American Rivers

“On Friday, August 3rd 2018, we began demolition of the 300 foot-long, 18 foot-high Columbia Dam. The Paulins Kill will run freely to meet the Delaware River for the first time in 109 years,” said New Jersey Nature Conservancy’s Beth Styler Barry. “The benefits of reconnecting these two freshwater ecosystems will be immediate and impact creatures that live in and near the stream, as well as people who come out to paddle, fish or enjoy the wildlife. Dam Removal projects are exciting, ecologically important and also a challenge, this project is a good example of partners coming together to get a great restoration project done.”

Because this is a big deal, we want to keep *YOU* updated on what’s happening from the field. Moving forward, we’ll post weekly blogs with scenes from the site.  Here’s a snapshot of what’s been happening over the last last two weeks:

August 1, 2018. Photo credit: Casey Schrading, Princeton Hydro

In order to make the first saw cut into the dam, Princeton Hydro and RiverLogic Solutions first identified the locations of the drill holes. These drill holes are used to feed the diamond wire through the dam for saw cutting.

August 1, 2018. Photo credit: Casey Schrading, Princeton Hydro

The crew placed the saw cutter machine on the staging area on top of the apron and prepared for the cut.

August 3, 2018. Photo credit: Princeton Hydro

In order to create a notch in the dam, the crew supplemented the saw cutting with hammering.

August 3, 2018. Photo Credit: The Nature Conservancy, Columbia Dam Volunteer Drone Team

August 3, 2018. Photo credit: Erik Sildorff, Delaware Riverkeeper Network

August 7, 2018. Photo credit: Casey Schrading, Princeton Hydro

Since the high water level was now higher than the bottom of the breach, water is able to flow in and over the notched section.

August 14, 2018. Photo credit: RiverLogic Solutions

Because of high flows of water from recent storm events, the dam breach is being widened to allow for larger flows of water to move downstream during high flow events. 

Additionally, a few weeks ago we reported on the lowering of the water levels and removal of the remnant dam downstream (below).

PHOTOS: Columbia Dam Removal

Since then, the remnant dam has been completed removed and the area has been stabilized.

July 23, 2018. Photo credit: Casey Schrading, Princeton Hydro

Now, the water can freely flow through this section of the Paulins Kill.

And, in case you missed it, we celebrated the commencement of the Columbia Dam removal with NJDEP’s Commissioner Catherine McCabe and our project partners. Full story below:

Celebrating the Columbia Dam Removal

Princeton Hydro has designed, permitted, and overseen the reconstruction, repair, and removal of a dozens of small and large dams in the Northeast. To learn more about our fish passage and dam removal engineering services, visitbit.ly/DamBarrier.

Lithuania Hosts First-ever Dam Removal Workshop Feat. Princeton Hydro Expert

Lithuania Hosts its First-Ever
Dam Removal Workshop

Princeton Hydro’s Laura Wildman Invited to Present

History was recently made in Lithuania with the occurrence of the first-ever dam removal workshop held in the country. Experts throughout the world convened at the Ministry of Environment in Vilnius, the capital of Lithuania, to lead discussions on a variety of topics related to dam removal and river rehabilitation.  They covered the current state of affairs regarding Lithuanian dams and showcased the Dam Removal Europe (DRE) initiative, a new effort aimed at restoring rivers in Europe.

The workshop was the brainchild of Lithuanian environmental activist Karolina Gurjazkaitė. She read about the DRE campaign and was so inspired by the initiative, she contacted DRE representatives about organizing the workshop. Her goals in organizing the first-ever dam removal workshop in Lithuania were to build awareness around the importance of river restoration, call attention to the many outdated, unmaintained, and unnecessary dams throughout Lithuania, and ultimately inspire positive changes in the way of dam removals and river rehabilitation.

“I am very excited, not only about the workshop, but also about the ‘side effects’…already created,” said Karolina. “People are gaining hopes and enthusiasm… This workshop may have really powerful outcomes!”

Karolina gathered a diverse group of workshop attendees, comprised of government officials (including the Vice-Minister of Environment of Lithuania), university professors (primarily specializing in dam safety and hydropower development), local environmental advocates and NGO volunteers, researchers, and students.

Presenters during the workshop included scientists, engineers, communication experts, planners, activists, and Princeton Hydro’s New England Regional Office Director and Fisheries Engineer Laura Wildman, P.E.

Presentations covered a wide variety of topics, including:

  • Policy and current situation in Europe: Pao Fernández Garrido of World Fish Migration Foundation, Spain presented on DRE findings related to policy and the current dam removal situation in Europe.

  • Research: Rachel Bowes from Karlstad University, Sweden spoke about current state of affairs with Swedish dam removal efforts and the research they are currently carrying out.

  • Book presentation: Herman Wanningen of World Fish Migration Foundation, Netherlands presented the new book, From Sea to Source 2.0, which is focused on tackling the challenges of restoring fish migration in rivers around the world and is available for free download.

  • Technical issues: Laura Wildman, PE, who has over 20 years of experience on dam removal, presented on the most important technical aspects when carrying out a barrier demolition.

On day two of the workshop, participants were invited to take part in field visits to five dam sites. Each of the five dams all presented their own unique challenges in terms of the ability to remove them. The site visits provided a deeper look into the challenges that will need to be addressed when forging ahead with a Lithuanian river restoration initiative.

The workshop proved to be instrumental in identifying key challenges and next steps in building a successful country-wide river rehabilitation initiative. One of the key takeaways from the workshop is the need for a more robust understanding of Lithuanian-specific rules and regulations that classify a dam removal project as either viable or not viable.

“Not only has there never been a dam removal workshop held in Lithuania, to date, a dam removal has never been completed in Lithuania, at least none that have been documented and none for environmental restoration reasons,” said Laura. “It’s clear that we still have a lot to explore and discover, but I am so thrilled to have been a part of this workshop. It was a very positive first step in the right direction, and I’m looking forward to watching and helping this initiative flourish.”

To learn more about Princeton Hydro’s dam removal and river restoration initiatives, go here.

 

Celebrating the Columbia Dam Removal

A view of the Columbia Dam at the beginning of the removal process.

On a bright, sunny day in Warren County, Princeton Hydro celebrated the Columbia Dam Removal Project with New Jersey Department of Environmental Protection (NJDEP) Commissioner Catherine McCabe, The New Jersey Nature Conservancy (event organizer), American Rivers, U.S. Fish and Wildlife Service (USFWS), NJDEP Division of Fish and Wildlife Service, RiverLogic Solutions, and SumCo Eco-Contracting.

Beth Styler-Barry, River Restoration Manager, New Jersey Nature Conservancy

Overlooking the soon-to-be removed, century-old, hydroelectric Columbia Dam, key stakeholders, including Princeton Hydro’s President Geoffrey Goll, P.E. and New Jersey Nature Conservancy’s Director Barbara Brummer, remarked on the success of the project, collaborative team efforts, and future benefits to the Paulins Kill habitat.

NJ Nature Conservancy’s River Restoration Manager, Beth Styler-Barry thanked project funders including NJDEP’s Office of Natural Resource Restoration, USFWS’s Fish Passage Program, National Fish and Wildlife Foundation’s Bring Back The Natives program, Natural Resources Conservation Service’s Regional Conservation Partnership Program, New Jersey Corporate Wetlands Restoration Partnership, Leavens Foundation, Tom’s of Maine, and Nature Conservancy members and donors.

“We made a commitment early-on to a 10-year monitoring and measurement plan. The removal of Columbia Dam is an opportunity to gain new knowledge and generate data that builds the case for this type of restoration. We’ll be looking at everything from mussels to temperature to geomorphological changes to increasing our targeted efficiencies. We’re also going to use images taken from repeated drone flyovers to look closely at changes in topography,” said Styler-Barry.

NJDEP Commissioner Catherine McCabe with NJ Division of Fish & Wildlife and NJDEP officials.

NJDEP Commissioner Catherine McCabe added, “The Columbia Dam is ranked in the top 5% of the nearly 14,000 dams that were assessed for priority. It will give us one of the most bangs for our buck in terms of fish and native species that we’ll be able to bring back up here.” She added, “This is exactly what Natural Resources Damages funds should be used for, and we are thrilled to see it come to fruition.”

Geoffrey Goll, P.E., President, Princeton Hydro

Back in the day, this dam structure was a marvel of engineering. Because concrete was very expensive during the time of construction, a patented, innovative “ransom hollow” design was used, which means it has a hollow center with series of doorways underneath the dam, explained Geoffrey Goll, P.E., President of Princeton Hydro. However, sustainability and climate change are very important issues today and must be taken into consideration for the life-cycle of a dam.

“Removal is a logical step in the history of this dam. Dam removals are the most impactful restorations. They provide the most ecological uplift and improvement for rivers,” Goll stated.

For Princeton Hydro, this project involved every discipline we have in the firm: civil engineering, fishery biology, wetland science, hydraulics, geotechnical engineering, and regulatory work. We were contracted by American Rivers to investigate, design, and permit for the removal of this dam for the New Jersey Nature Conservancy. Our team of engineers and ecologists studied the feasibility of removal by collecting sediment samples, performed bioassay tests, and conducted a hydraulic analysis of upstream and downstream conditions. Currently, we are providing construction administration services during the removal process. This project is a great example of our ability to complete multi-disciplinary projects in-house.

Project partners ready for the first hammer with the celebratory dynamite and sledge hammers.

At the end of the press conference, project partners celebrated the anticipation of the “first hammer” in the near future with an imitation dynamite siren and plastic sledge hammers. It was truly a keystone moment for everyone involved in this project.

The remnant dam downstream has already been removed and the main dam is due to be removed very soon. Check out our previous story with a series of photos documenting this first-step in the overall dam removal process: bit.ly/ColumbiaDamRemoval. Stay tuned for photos during the main dam removal process too.

Princeton Hydro has designed, permitted, and overseen the reconstruction, repair, and removal of a dozens of small and large dams in the Northeast. To learn more about our fish passage and dam removal engineering services, visitbit.ly/DamBarrier.

Conservation Spotlight: Dunes at Shoal Harbor Shoreline Protection

Hurricane Sandy was the largest storm to ever originate in the Atlantic ocean. It badly damaged several countries in the Caribbean, caused over $50 billion in damages along the Eastern Seaboard, and left dozens dead. While hurricanes are a natural part of our climate system, research shows that intense hurricane activity has been on the rise in the North Atlantic since the 1970s. This trend is likely to be exacerbated by sea level rise and growing populations along coastlines. Natural coastal habitats — like wetlands and dunes — have proven to shield people from storms and sea-level rise, and have protected coastal communities from hundreds of millions of dollars in damage.

The Dunes at Shoal Harbor, a residential community in Monmouth County, New Jersey, is situated adjacent to both the Raritan Bay and the New York City Ferry channel. The site, previously utilized for industrial purposes, consisted of a partially demolished docking/berthing facility. A significantly undersized 6” diameter, 8-foot long stone revetment was also constructed on the property.

During Hurricane Sandy, the revetment failed and the community was subjected to direct wave attack and flooding. Homes were damaged, beach access was impaired, and the existing site-wide stormwater management basin and outfall was completely destroyed.

Princeton Hydro performed a wave attack analysis commensurate with a category three hurricane event, and used that data to complete a site design for shoreline protection. Consistent with the analysis, the site design includes the installation of a 15-foot rock revetment (one foot above the 100-year floodplain elevation) constructed with four-foot diameter boulders. The project also consists of replacing a failed elevated timber walkway with a concrete slab-on-grade walkway, restoring portions of the existing bulkhead, clearing invasive plants, and the complete restoration of the failed stormwater basin and outlet.

A rendering of the “Dunes at Shoal Harbor” shoreline protection design by Princeton Hydro.

The plan incorporates natural barriers to reduce the impacts of storm surges and protect the coastal community, including planting stabilizing coastal vegetation to prevent erosion and installing fencing along the dune to facilitate natural dune growth.

These measures will discourage future erosion of the shoreline, protect the residential community from future wave attacks and flooding, and create a stable habitat for native and migratory species.  The project is currently in the permitting phase, and will move to construction when all permits are obtained from local, state, and federal agencies.

This project is an great example of Princeton Hydro’s ability to coordinate multi-disciplinary projects in-house. Our Water Resources Engineering, Geosciences Engineering, and Natural Resources teams have collaborated efficiently to analyze, design, and permit this shoreline protection project. For more information on our engineering services, go here.

PHOTOS: Columbia Dam Removal

VIDEO: “Columbia Lake Dam when the water level was 18 inches to 2 feet lower”
Video courtesy of Matt Hencheck

In Northwest New Jersey on the Paulins Kill, an important tributary to the Delaware River, the century-old hydroelectric Columbia Dam is actively being removed. Princeton Hydro was contracted by American Rivers to investigate, design, and apply for permits for the removal of this dam for the New Jersey chapter of The Nature Conservancy. Our team of engineers and ecologists studied the feasibility of removal by collecting sediment samples, performing bioassay tests, and conducting a hydraulic analysis of upstream and downstream conditions. We’re excited to report that the Columbia Dam removal has officially commenced!

The New Jersey Department of Environmental Protection started draining water from Columbia Lake a few weeks ago, which was the first step in removing the dam. Princeton Hydro has subsequently been contracted by The Nature Conservancy to provide construction administration services.  Photos below show the water at lowered levels at the impoundments.

“Dewatering Impoundment” Photo by Princeton Hydro

“An aerial drone snapshot when water levels were down about 5 feet at the upper impoundment” Photo courtesy of the New Jersey Chapter of The Nature Conservancy

Last week, the first hammer hit the wall of a downstream dam remnant, officially starting the removal process.

“The first hammer”  Photo courtesy of Dale Bentz, RiverLogic Solutions

The dam removal process will last a few weeks, as the contractor actively knocks down the thick concrete wall.

“Pressure and time”  Photo courtesy of Dale Bentz, RiverLogic Solutions

“Halfway there”  Photo courtesy of Dale Bentz, RiverLogic Solutions

Once the dam is removed, there is a high probability that populations of American Shad and River Herring will be restored. It may also enhance American Eel migration. As a coldwater fishery, this reach also has significant potential for trout species, as well as Smallmouth Bass.

(Top) Before: Photo of the Columbia Dam before construction. (Bottom) After: Princeton Hydro’s rendering of what the river will look like once the dam is removed.

“It is very exciting to be a part of such a monumental effort for the restoration of the Paulins Kill. This river, once a major migration route for diadromous fish like American Shad, will once again be a nursery for this Delaware River icon,” said Geoffrey Goll, PE, President and co-founder of Princeton Hydro. “The removal of these dams will also restore the functions and values of a riparian corridor and floodplain, eliminate costs to the taxpayer for the maintenance of a dam and lake, and provide additional riverine recreational opportunities. I expect to see the same resilience and positive impact to the Delaware River as the recent barrier removals on another major NJ tributary, the Musconetcong River. It is a win-win for NJ, and with The Nature Conservancy at the helm and expert guidance from American Rivers, it has been an experience of a career.”

This project could not have been possible without the hard work and dedication of the following partner organizations: The Nature Conservancy of New Jersey, American Rivers, U.S. Fish and Wildlife Service, RiverLogic Solutions, NJDEP Division of Fish and Wildlife Service, and SumCo EcoContracting.

Princeton Hydro has designed, permitted, and overseen the reconstruction, repair, and removal of a dozens of small and large dams in the Northeast. To learn more about our fish passage and dam removal engineering services, visitbit.ly/DamBarrier.


This video from 2016 features the Nature Conservancy’s New Jersey State Director Barbara Brummer, Ph.D. speaking on the Columbia Dam removal. Video credit: NJ Herald.