UPDATE: The Columbia Dam Is Coming Down

It’s happening! The Columbia Dam on the Paulins Kill in Northern New Jersey is finally coming down thanks to a successful collaboration between The Nature Conservancy, American Rivers, U.S. Fish and Wildlife Service, NJDEP Division of Fish and Wildlife Service, and Princeton Hydro. The first cut on the main dam wall was made just two weeks ago, and the water has started flowing downstream as the concrete is slowly being removed by the contractors RiverLogic Solutions and SumCo Eco-Contracting.

“In New Jersey, successful dam removal projects are often the result of partnerships between nonprofit organizations, federal and state agencies, consultants, and others working together toward the common goal of river restoration,” exclaimed Dr. Laura Craig, Director of River Restoration, American Rivers. “The first day of dam demolition is always a joyous occasion for project partners, but I was especially happy to see the river flowing through the breached Columbia Dam for the first time after working so intensely on this project for the last few years.”

Princeton Hydro has been involved with the engineering and restoration design from the beginning, so we’re very excited to report on this major update.  Our team of engineers and ecologists studied the feasibility of removal as requested by American Rivers in partnership with the New Jersey chapter of The Nature Conservancy.  We investigated, designed, and prepared the necessary permits for the removal of this dam. And, now we’ve been subsequently been hired to provide construction administration services during the removal process, which means we get to see the dam come down firsthand, piece by piece!

“It is truly amazing and exciting to finally see the main and remnant dams come down, as I have been involved in this restoration effort since the feasibility stage,” said Kelly Klein, Senior Project Manager, Princeton Hydro. “I am so honored to be part of this dynamic team and to collaborate with our project partners during every stage of this dam removal.”

Geoff Goll, Princeton Hydro and Beth Styler Barry, The Nature Conservancy on site August 3, 2018. Photo credit: Laura Craig, American Rivers

“On Friday, August 3rd 2018, we began demolition of the 300 foot-long, 18 foot-high Columbia Dam. The Paulins Kill will run freely to meet the Delaware River for the first time in 109 years,” said New Jersey Nature Conservancy’s Beth Styler Barry. “The benefits of reconnecting these two freshwater ecosystems will be immediate and impact creatures that live in and near the stream, as well as people who come out to paddle, fish or enjoy the wildlife. Dam Removal projects are exciting, ecologically important and also a challenge, this project is a good example of partners coming together to get a great restoration project done.”

Because this is a big deal, we want to keep *YOU* updated on what’s happening from the field. Moving forward, we’ll post weekly blogs with scenes from the site.  Here’s a snapshot of what’s been happening over the last last two weeks:

August 1, 2018. Photo credit: Casey Schrading, Princeton Hydro

In order to make the first saw cut into the dam, Princeton Hydro and RiverLogic Solutions first identified the locations of the drill holes. These drill holes are used to feed the diamond wire through the dam for saw cutting.

August 1, 2018. Photo credit: Casey Schrading, Princeton Hydro

The crew placed the saw cutter machine on the staging area on top of the apron and prepared for the cut.

August 3, 2018. Photo credit: Princeton Hydro

In order to create a notch in the dam, the crew supplemented the saw cutting with hammering.

August 3, 2018. Photo Credit: The Nature Conservancy, Columbia Dam Volunteer Drone Team

August 3, 2018. Photo credit: Erik Sildorff, Delaware Riverkeeper Network

August 7, 2018. Photo credit: Casey Schrading, Princeton Hydro

Since the high water level was now higher than the bottom of the breach, water is able to flow in and over the notched section.

August 14, 2018. Photo credit: RiverLogic Solutions

Because of high flows of water from recent storm events, the dam breach is being widened to allow for larger flows of water to move downstream during high flow events. 

Additionally, a few weeks ago we reported on the lowering of the water levels and removal of the remnant dam downstream (below).

PHOTOS: Columbia Dam Removal

Since then, the remnant dam has been completed removed and the area has been stabilized.

July 23, 2018. Photo credit: Casey Schrading, Princeton Hydro

Now, the water can freely flow through this section of the Paulins Kill.

And, in case you missed it, we celebrated the commencement of the Columbia Dam removal with NJDEP’s Commissioner Catherine McCabe and our project partners. Full story below:

Celebrating the Columbia Dam Removal

Princeton Hydro has designed, permitted, and overseen the reconstruction, repair, and removal of a dozens of small and large dams in the Northeast. To learn more about our fish passage and dam removal engineering services, visitbit.ly/DamBarrier.

Lithuania Hosts First-ever Dam Removal Workshop Feat. Princeton Hydro Expert

Lithuania Hosts its First-Ever
Dam Removal Workshop

Princeton Hydro’s Laura Wildman Invited to Present

History was recently made in Lithuania with the occurrence of the first-ever dam removal workshop held in the country. Experts throughout the world convened at the Ministry of Environment in Vilnius, the capital of Lithuania, to lead discussions on a variety of topics related to dam removal and river rehabilitation.  They covered the current state of affairs regarding Lithuanian dams and showcased the Dam Removal Europe (DRE) initiative, a new effort aimed at restoring rivers in Europe.

The workshop was the brainchild of Lithuanian environmental activist Karolina Gurjazkaitė. She read about the DRE campaign and was so inspired by the initiative, she contacted DRE representatives about organizing the workshop. Her goals in organizing the first-ever dam removal workshop in Lithuania were to build awareness around the importance of river restoration, call attention to the many outdated, unmaintained, and unnecessary dams throughout Lithuania, and ultimately inspire positive changes in the way of dam removals and river rehabilitation.

“I am very excited, not only about the workshop, but also about the ‘side effects’…already created,” said Karolina. “People are gaining hopes and enthusiasm… This workshop may have really powerful outcomes!”

Karolina gathered a diverse group of workshop attendees, comprised of government officials (including the Vice-Minister of Environment of Lithuania), university professors (primarily specializing in dam safety and hydropower development), local environmental advocates and NGO volunteers, researchers, and students.

Presenters during the workshop included scientists, engineers, communication experts, planners, activists, and Princeton Hydro’s New England Regional Office Director and Fisheries Engineer Laura Wildman, P.E.

Presentations covered a wide variety of topics, including:

  • Policy and current situation in Europe: Pao Fernández Garrido of World Fish Migration Foundation, Spain presented on DRE findings related to policy and the current dam removal situation in Europe.

  • Research: Rachel Bowes from Karlstad University, Sweden spoke about current state of affairs with Swedish dam removal efforts and the research they are currently carrying out.

  • Book presentation: Herman Wanningen of World Fish Migration Foundation, Netherlands presented the new book, From Sea to Source 2.0, which is focused on tackling the challenges of restoring fish migration in rivers around the world and is available for free download.

  • Technical issues: Laura Wildman, PE, who has over 20 years of experience on dam removal, presented on the most important technical aspects when carrying out a barrier demolition.

On day two of the workshop, participants were invited to take part in field visits to five dam sites. Each of the five dams all presented their own unique challenges in terms of the ability to remove them. The site visits provided a deeper look into the challenges that will need to be addressed when forging ahead with a Lithuanian river restoration initiative.

The workshop proved to be instrumental in identifying key challenges and next steps in building a successful country-wide river rehabilitation initiative. One of the key takeaways from the workshop is the need for a more robust understanding of Lithuanian-specific rules and regulations that classify a dam removal project as either viable or not viable.

“Not only has there never been a dam removal workshop held in Lithuania, to date, a dam removal has never been completed in Lithuania, at least none that have been documented and none for environmental restoration reasons,” said Laura. “It’s clear that we still have a lot to explore and discover, but I am so thrilled to have been a part of this workshop. It was a very positive first step in the right direction, and I’m looking forward to watching and helping this initiative flourish.”

To learn more about Princeton Hydro’s dam removal and river restoration initiatives, go here.

 

Celebrating the Columbia Dam Removal

A view of the Columbia Dam at the beginning of the removal process.

On a bright, sunny day in Warren County, Princeton Hydro celebrated the Columbia Dam Removal Project with New Jersey Department of Environmental Protection (NJDEP) Commissioner Catherine McCabe, The New Jersey Nature Conservancy (event organizer), American Rivers, U.S. Fish and Wildlife Service (USFWS), NJDEP Division of Fish and Wildlife Service, RiverLogic Solutions, and SumCo Eco-Contracting.

Beth Styler-Barry, River Restoration Manager, New Jersey Nature Conservancy

Overlooking the soon-to-be removed, century-old, hydroelectric Columbia Dam, key stakeholders, including Princeton Hydro’s President Geoffrey Goll, P.E. and New Jersey Nature Conservancy’s Director Barbara Brummer, remarked on the success of the project, collaborative team efforts, and future benefits to the Paulins Kill habitat.

NJ Nature Conservancy’s River Restoration Manager, Beth Styler-Barry thanked project funders including NJDEP’s Office of Natural Resource Restoration, USFWS’s Fish Passage Program, National Fish and Wildlife Foundation’s Bring Back The Natives program, Natural Resources Conservation Service’s Regional Conservation Partnership Program, New Jersey Corporate Wetlands Restoration Partnership, Leavens Foundation, Tom’s of Maine, and Nature Conservancy members and donors.

“We made a commitment early-on to a 10-year monitoring and measurement plan. The removal of Columbia Dam is an opportunity to gain new knowledge and generate data that builds the case for this type of restoration. We’ll be looking at everything from mussels to temperature to geomorphological changes to increasing our targeted efficiencies. We’re also going to use images taken from repeated drone flyovers to look closely at changes in topography,” said Styler-Barry.

NJDEP Commissioner Catherine McCabe with NJ Division of Fish & Wildlife and NJDEP officials.

NJDEP Commissioner Catherine McCabe added, “The Columbia Dam is ranked in the top 5% of the nearly 14,000 dams that were assessed for priority. It will give us one of the most bangs for our buck in terms of fish and native species that we’ll be able to bring back up here.” She added, “This is exactly what Natural Resources Damages funds should be used for, and we are thrilled to see it come to fruition.”

Geoffrey Goll, P.E., President, Princeton Hydro

Back in the day, this dam structure was a marvel of engineering. Because concrete was very expensive during the time of construction, a patented, innovative “ransom hollow” design was used, which means it has a hollow center with series of doorways underneath the dam, explained Geoffrey Goll, P.E., President of Princeton Hydro. However, sustainability and climate change are very important issues today and must be taken into consideration for the life-cycle of a dam.

“Removal is a logical step in the history of this dam. Dam removals are the most impactful restorations. They provide the most ecological uplift and improvement for rivers,” Goll stated.

For Princeton Hydro, this project involved every discipline we have in the firm: civil engineering, fishery biology, wetland science, hydraulics, geotechnical engineering, and regulatory work. We were contracted by American Rivers to investigate, design, and permit for the removal of this dam for the New Jersey Nature Conservancy. Our team of engineers and ecologists studied the feasibility of removal by collecting sediment samples, performed bioassay tests, and conducted a hydraulic analysis of upstream and downstream conditions. Currently, we are providing construction administration services during the removal process. This project is a great example of our ability to complete multi-disciplinary projects in-house.

Project partners ready for the first hammer with the celebratory dynamite and sledge hammers.

At the end of the press conference, project partners celebrated the anticipation of the “first hammer” in the near future with an imitation dynamite siren and plastic sledge hammers. It was truly a keystone moment for everyone involved in this project.

The remnant dam downstream has already been removed and the main dam is due to be removed very soon. Check out our previous story with a series of photos documenting this first-step in the overall dam removal process: bit.ly/ColumbiaDamRemoval. Stay tuned for photos during the main dam removal process too.

Princeton Hydro has designed, permitted, and overseen the reconstruction, repair, and removal of a dozens of small and large dams in the Northeast. To learn more about our fish passage and dam removal engineering services, visitbit.ly/DamBarrier.

Conservation Spotlight: Dunes at Shoal Harbor Shoreline Protection

Hurricane Sandy was the largest storm to ever originate in the Atlantic ocean. It badly damaged several countries in the Caribbean, caused over $50 billion in damages along the Eastern Seaboard, and left dozens dead. While hurricanes are a natural part of our climate system, research shows that intense hurricane activity has been on the rise in the North Atlantic since the 1970s. This trend is likely to be exacerbated by sea level rise and growing populations along coastlines. Natural coastal habitats — like wetlands and dunes — have proven to shield people from storms and sea-level rise, and have protected coastal communities from hundreds of millions of dollars in damage.

The Dunes at Shoal Harbor, a residential community in Monmouth County, New Jersey, is situated adjacent to both the Raritan Bay and the New York City Ferry channel. The site, previously utilized for industrial purposes, consisted of a partially demolished docking/berthing facility. A significantly undersized 6” diameter, 8-foot long stone revetment was also constructed on the property.

During Hurricane Sandy, the revetment failed and the community was subjected to direct wave attack and flooding. Homes were damaged, beach access was impaired, and the existing site-wide stormwater management basin and outfall was completely destroyed.

Princeton Hydro performed a wave attack analysis commensurate with a category three hurricane event, and used that data to complete a site design for shoreline protection. Consistent with the analysis, the site design includes the installation of a 15-foot rock revetment (one foot above the 100-year floodplain elevation) constructed with four-foot diameter boulders. The project also consists of replacing a failed elevated timber walkway with a concrete slab-on-grade walkway, restoring portions of the existing bulkhead, clearing invasive plants, and the complete restoration of the failed stormwater basin and outlet.

A rendering of the “Dunes at Shoal Harbor” shoreline protection design by Princeton Hydro.

The plan incorporates natural barriers to reduce the impacts of storm surges and protect the coastal community, including planting stabilizing coastal vegetation to prevent erosion and installing fencing along the dune to facilitate natural dune growth.

These measures will discourage future erosion of the shoreline, protect the residential community from future wave attacks and flooding, and create a stable habitat for native and migratory species.  The project is currently in the permitting phase, and will move to construction when all permits are obtained from local, state, and federal agencies.

This project is an great example of Princeton Hydro’s ability to coordinate multi-disciplinary projects in-house. Our Water Resources Engineering, Geosciences Engineering, and Natural Resources teams have collaborated efficiently to analyze, design, and permit this shoreline protection project. For more information on our engineering services, go here.

PHOTOS: Columbia Dam Removal

VIDEO: “Columbia Lake Dam when the water level was 18 inches to 2 feet lower”
Video courtesy of Matt Hencheck

In Northwest New Jersey on the Paulins Kill, an important tributary to the Delaware River, the century-old hydroelectric Columbia Dam is actively being removed. Princeton Hydro was contracted by American Rivers to investigate, design, and apply for permits for the removal of this dam for the New Jersey chapter of The Nature Conservancy. Our team of engineers and ecologists studied the feasibility of removal by collecting sediment samples, performing bioassay tests, and conducting a hydraulic analysis of upstream and downstream conditions. We’re excited to report that the Columbia Dam removal has officially commenced!

The New Jersey Department of Environmental Protection started draining water from Columbia Lake a few weeks ago, which was the first step in removing the dam. Princeton Hydro has subsequently been contracted by The Nature Conservancy to provide construction administration services.  Photos below show the water at lowered levels at the impoundments.

“Dewatering Impoundment” Photo by Princeton Hydro

“An aerial drone snapshot when water levels were down about 5 feet at the upper impoundment” Photo courtesy of the New Jersey Chapter of The Nature Conservancy

Last week, the first hammer hit the wall of a downstream dam remnant, officially starting the removal process.

“The first hammer”  Photo courtesy of Dale Bentz, RiverLogic Solutions

The dam removal process will last a few weeks, as the contractor actively knocks down the thick concrete wall.

“Pressure and time”  Photo courtesy of Dale Bentz, RiverLogic Solutions

“Halfway there”  Photo courtesy of Dale Bentz, RiverLogic Solutions

Once the dam is removed, there is a high probability that populations of American Shad and River Herring will be restored. It may also enhance American Eel migration. As a coldwater fishery, this reach also has significant potential for trout species, as well as Smallmouth Bass.

(Top) Before: Photo of the Columbia Dam before construction. (Bottom) After: Princeton Hydro’s rendering of what the river will look like once the dam is removed.

“It is very exciting to be a part of such a monumental effort for the restoration of the Paulins Kill. This river, once a major migration route for diadromous fish like American Shad, will once again be a nursery for this Delaware River icon,” said Geoffrey Goll, PE, President and co-founder of Princeton Hydro. “The removal of these dams will also restore the functions and values of a riparian corridor and floodplain, eliminate costs to the taxpayer for the maintenance of a dam and lake, and provide additional riverine recreational opportunities. I expect to see the same resilience and positive impact to the Delaware River as the recent barrier removals on another major NJ tributary, the Musconetcong River. It is a win-win for NJ, and with The Nature Conservancy at the helm and expert guidance from American Rivers, it has been an experience of a career.”

This project could not have been possible without the hard work and dedication of the following partner organizations: The Nature Conservancy of New Jersey, American Rivers, U.S. Fish and Wildlife Service, RiverLogic Solutions, NJDEP Division of Fish and Wildlife Service, and SumCo EcoContracting.

Princeton Hydro has designed, permitted, and overseen the reconstruction, repair, and removal of a dozens of small and large dams in the Northeast. To learn more about our fish passage and dam removal engineering services, visitbit.ly/DamBarrier.


This video from 2016 features the Nature Conservancy’s New Jersey State Director Barbara Brummer, Ph.D. speaking on the Columbia Dam removal. Video credit: NJ Herald.

Dam Removal on the Moosup River

Moosup River

The Moosup River is a beautiful 30-mile-long, trout river flowing through Connecticut and Rhode Island, eventually emptying into the Quinebaug River.

Several dams, most originally built in the 1800s or early 1900s, impeded the river’s natural flow, impaired habitat, fragmented the river system, and prevented fish from swimming upstream to their native spawning grounds.

In 2013, American Rivers, CTDEEP Fisheries, and Natural Resources Conservation Service began collaborating on the removal of multiple dams and remnant dams as part of a larger project to restore connectivity to the Moosup River in the Town of Plainfield. Princeton Hydro and RiverLogic Solutions were contracted to provide design-build and permitting services.

As part of this larger multi-year effort, five dams are planned for removal from the Moosup River. The most downstream barrier, the Hale Factory Dam was removed in 2014. The remnants of the toppled Griswold Rubber Dam were removed in 2015. In 2017, the removal of Brunswick Mill Dam #1 was completed. And, two more dams, downstream of New Brunswick Mill Dam #1, are currently under consideration for removal. When fully completed, the Moosup River Dam Removal Project will reconnect fish habitats along 6.9 miles of the Moosup River.

 

Hale Factory Dam

The Hale Factory Dam was constructed of a boulder core capped in a one-foot-thick concrete layer. The dam was partially breached as the concrete cap had deteriorated severely over the years, allowing flow to pass between boulders and allowing the normal pool elevation to drop substantially from its former design height.

The resource delineation conducted on site identified a vernal pool with an 18 inch culvert outlet that discharged 90 feet upstream of the dam. To preserve this ecological resource on the site, the vernal pool was not disturbed during the dam removal.

Princeton Hydro provided a field assessment, sediment characterization and analysis, final design and permit application package for the full removal of the Hale Factory Dam. Full removal of the dam entailed demolition and removal of the concrete, and re-use of the natural cobbles and boulders from the dam to create in-stream habitat features. Once completed, the river and its boulders appeared as if placed by nature itself, with the former dam’s presence indicated only by the age-old lichen covered field stone walls leading up to the banks.

 

Griswold Rubber Dam

The Griswold Rubber Dam was in a gravel-cobble reach of the river approximately 80 feet wide in the Village of Moosup and was adjacent to the 1992 expansion of the Griswold Rubber factory.  At one time, the dam stood approximately 10 feet high and 150 feet long. The dam was constructed of a large segmented concrete slab that had since toppled over and was lying nearly flat on the river bed in multiple sections. The dam structure, having failed, served no useful purpose. Despite being toppled, the dam still presented a deterrent to the effective movement of aquatic organisms at normal to low flows and was therefore worthy of complete removal to restore river connectivity.

Princeton Hydro conducted an initial field investigation with RiverLogic Solutions to gain insights regarding the construction approach. Princeton Hydro then followed-up with a more detailed assessment of river bed sediment, geomorphic conditions, the likely riverine response, construction access, and other design related issues that were incorporated into design plans and permit applications. The restoration design Princeton Hydro developed aimed to remove the partial barrier to fish passage with as little disturbance to surrounding infrastructure and resources as possible.

 

Brunswick Mill Dam #1

This dilapidated timber crib dam stood approximately 4-feet high and spanned the channel at approximately 130 feet. The timbers ranged from 1.5 to 2.5 feet in diameter and over 20 feet in length; 50 were integrated into the dam. The timber crib was filled with gravel and other debris, and the gravel substrate extended 50 feet upstream. The original dam was significantly higher, but the timber crib spillway deteriorated and gradually collapsed over time and only a portion of the structure remained.

For this project, Princeton Hydro completed sediment investigation, sampling and analysis; hydrologic and hydraulic analysis; and provided design and engineering for full removal of the dam. Princeton Hydro contracted with an archeologist / industrial historian, and together closely observed the dam deconstruction to observe and record how the timber crib had been assembled. Multiple types of iron pins and wooden pegs revealed how the dam had been repaired over the years – findings, old maps, and photos were incorporated into a historical report filed with the state historic preservation office. Princeton Hydro coordinated to have the old timbers salvaged for eventual re-use. Removing the Brunswick Mill Dam #1 was a continuation of the large scale Moosup River restoration effort and paved the way for the potential removal of two more dams downstream in the coming years.

“When a dam is breached and taken out, the tangible results are very quickly noticeable,” said Paul Woodworth, Princeton Hydro Fluvial Geomorphologist. “The return of migratory fish is a very strong indicator of the ecological benefits of dam removal – sometimes after a removal you can see fish immediately swimming upstream. Removing dams also improves safety in nearby communities, reestablishes the natural flow of sediment, improves water quality, provides new recreation opportunities, and restores habitats for fish and wildlife.”

Click here to read more about Princeton Hydro’s engineering services for the restoration and removal of dams.

EMPLOYEE SPOTLIGHT: Meet the Interns

This summer, Princeton Hydro is hosting five interns, each of whom are passionate about protecting water quality and preserving our natural resources. From June to August, our interns will gain professional work experience in a variety of subject areas, ranging from stormwater management to dam restoration to ecological design to lake management and much more. They are assisting on a variety of projects, getting real-world practice in their areas of study, and working with a Princeton Hydro mentor who is helping them gain a deeper understanding of the business of environmental and engineering consulting and setting them up for career success.

 

Meet Our Interns:

 

Ivy Babson, Environmental Science Intern

Ivy is a rising senior from University of Vermont, majoring in Environmental Science with a concentration in Ecological Design, and minor in Geospatial Technologies. In the future, she hopes to implement ecological design in urban areas and create a sustainable environment that would allow future generations to care for and interact with a healthy earth.

Ivy will work alongside Senior Aquatics Scientist Dr. Jack Szczepanski and the Princeton Hydro Aquatics team on projects related to lake and pond management, including fisheries management, data collection and analysis, and water quality monitoring. Recently, Ivy assisted Aquatic Ecologist Jesse Smith in completing an electrofishing survey in a Northern New Jersey river.

Learn more about Ivy.

 

Marissa Ciocco, Geotechnical Intern

Marissa is entering her fourth year at Rowan University where she is a Civil and Environmental Engineering major with a Bantivoglio Honors Concentration. In the future, Marissa hopes to work towards creating a greener and safer environment.

During her internship, Marissa will be mentored by Jim Hunt P.E., Geotechnical Engineer, who has already engaged Marissa in a few construction oversight projects, including a culvert restoration effort in Medford Lakes, NJ and observing geotechnical borings in Evesham, NJ.

Learn more about Marissa.

 

Will Kelleher, Environmental Science Intern

Will is a rising junior at the University of Vermont, studying Environmental Science with a concentration in Water Resources. His current career interests are focused around wetlands restoration and water chemistry. He recently spent two weeks studying water management and sustainable technology in the Netherlands and in the past has helped with biological and chemical stream monitoring with Raritan Headwaters Association.

Mentored by Senior Aquatics Scientist Dr. Jack Szczepanski, Will’s area of focus will be lake and pond management. He’ll spend most of his time in the field alongside members of the Aquatics Team collecting water quality data and mapping aquatic plants, learning about aquatic habitat creation, and implementing various invasive aquatic weed control efforts.

Learn more about Will.

 

Veronica Moditz, Water Resources Intern

We are thrilled to welcome back Veronica, who interned with us last year, and is in her final year at Stevens Institute of Technology, pursuing a Bachelor Degree in Environmental Engineering and a Master Degree in Sustainability Management. She is currently the secretary for Steven’s Environmental Engineering Professional Society chapter. In the future, she hopes to work on more sustainable approach to engineering problems.

Veronica will work alongside Project Engineer and Construction Specialist Amy McNamara, EIT, and Mary L. Paist-Goldman, P.E., Director of Engineering Services, on a variety of environmental engineering projects. Most recently, she assisted with a construction oversight and stormwater management project in Morris County, NJ.

Learn more about Veronica.

 

Tucker Simmons, Water Resources Engineer

Tucker is a Civil and Environmental Engineering major at Rowan University focusing on Water Resources Engineering. His Junior Clinic experience includes the study of Bio-Cemented sand and the Remote Sensing of Landfill Fires. In the future, Tucker hopes to work on creating a more sustainable environment.

Throughout his internship, Tucker will be mentored by Dr. Clay Emerson, P.E. CFM, Senior Water Resources Engineer, and will work on projects related to stormwater management, hydrologic and hydraulic analysis, and various aspects of environmental restoration. He recently assisted with a sink hole inspection in Tredyffrin Township, PA and mapped the water depths of a lake in Bucks County, PA.

Learn more about Tucker.

 

Stay tuned for updates on what our interns are working on!

 

 

 

Princeton Hydro Supports Creation of Stormwater Utilities in New Jersey

For Immediate Release: May 15, 2018

PRESS STATEMENT 

On behalf of Princeton Hydro, LLC, a leading water resources engineering and natural resource management small business firm in New Jersey, we support the passing of New Jersey’s stormwater utility creation bill, S-1073. If S-1073 is administered in a responsible manner, we believe that it will enhance water quality and reduce flooding impacts in New Jersey.

Since our inception, Princeton Hydro has been a leader in innovative, cost-effective, and environmentally sound stormwater management. Long before the term “green infrastructure” was part of the design community’s lexicon, our engineers were integrating stormwater management with natural systems to fulfill such diverse objectives as flood control, water quality protection, and pollutant reduction. Our staff has developed regional nonpoint source pollutant budgets for over 100 waterways. The preparation of stormwater management plans and design of stormwater management systems for pollutant reduction is an integral part of many of our projects.

We have seen the benefits of allowing for stormwater utilities firsthand. In Maryland, the recently implemented watershed restoration program and MS4 efforts that require stormwater utility fees have provided a job creating-industry boom that benefits engineers, contractors, and local DPWs. At the same time, Maryland’s program is improving the water quality in the Chesapeake Bay, and stimulating the tourism and the crabbing/fishing industry.

New Jersey has the very same issues with our water resources as Maryland. Just like the Chesapeake Bay, our Barnegat Bay, Raritan Bay, and Lake Hopatcong have serious issues with stormwater runoff that is degrading our water quality and quality of life.  Our stormwater infrastructure is old and falling apart, and all stormwater utilities need continual maintenance to save money in the long run.

It is important to point out that this current bill is not a mandatory requirement, and would simply provide a mechanism for various levels of government (county, municipality, etc.) to collect a stormwater utility fee in order to recover runoff management costs.

This bill (S-1073) should not be reviewed only in the context of cost, as this bill meets all three elements of the  triple-bottom line of sustainability; social, environmental, and financial. Allowing stormwater utilities in New Jersey will create jobs, help reduce flood impacts, enhance water quality, improve our fisheries, and preserve our water-based tourism economy. 40 states have already implemented stormwater utilities, and we believe that it is time for New Jersey to join the ranks.

###

Conservation Spotlight: Restoring Fish Passage on the Noroton River

For thousands of years, river herring swam from the Atlantic Ocean through the Long Island Sound and up the Noroton River to spawn each spring. Then, they returned to the ocean until the next spawning season.

Back in the 1920s, President Dwight D. Eisenhower’s administration began connecting the country through a massive interstate highway system. As part of the infrastructure plan, hundreds of thousands of culverts were built across the U.S. with the intention of moving water quickly and efficiently. While that goal was met, many migratory fish and other aquatic organisms could not overcome the culverts’ high-velocity flows, shallow water depths, and perched outlets. This infrastructure prevented them from reaching their native migratory destinations.

By the late 1950s, Interstate 95 cut through Connecticut’s coastal rivers, and culverts were installed to convey river flows. Alewives, American Shad, Blueback Herring, and other native fish species were unable to navigate the culverts. Their populations dwindled to the point where Connecticut, along with Rhode Island, Massachusetts, and North Carolina, instituted moratoriums on catching and keeping the valued forage fish.

Along the Noroton River, three parallel concrete culverts, each 300-feet long, 13-feet wide and 7-feet in height were installed, completely blocking upstream fish passage.  In order to restore important fish populations and revitalize the Noroton River, Save the Sound launched a project that reopened approximately seven miles of the river, allowing migratory fish populations to safely and easily travel through the culverts to reach their original spawning habitat upstream.

The project is a collaboration among Save the Sound, Darien Land Trust, Connecticut Department of Energy and Environmental Protection (CTDEEP), Connecticut Department of Transportation, Princeton Hydro, and other partners. For the project, Princeton Hydro lead design engineering and guided the construction of the following elements to restore upstream fish passage:

  • The installation of a concrete weir at the upstream end of the culvert to increase water depths in one culvert during low-flow periods;
  • The installation of concrete baffles to reduce flow velocities and create resting places for fish, and;
  • The installation of a naturalized, step-pool, rock ramp at the downstream end of the project to allow fish to ascend into the culvert gradually, overcoming the two-foot vertical drop present under existing conditions. The rock ramp consists of a grouted riverstone base with large grouted boulders arranged to make steps, with low-flow passage channels, between a series of pools approximately 1-foot deep that create resting places for upstream migrating fish.

Reopening river passage for migratory species will improve not only the health of the Noroton River itself, but will also benefit the overall ecosystem of Long Island Sound. Over the last decade, fish passage projects around the sound’s Connecticut and New York shores have dramatically increased freshwater spawning habitat for the foundational species whose return is restoring a more vibrant food web to the Long Island Sound.

Construction of the baffles and rock ramp were completed in time for the 2018 migratory season. Construction of the concrete weir is on temporary hold for low-flow conditions. On April 26, 2018, project partners gathered for a project celebration and the release of migratory fish by CTDEEP at an upstream location.

“It’s fascinating to feel the change in the flow patterns against your legs as you walk through the baffled culvert knowing that it will now facilitate fish passage through this restored reach,” said Princeton Hydro’s New England Regional Office Director and Water Resources and Fisheries Engineer Laura Wildman, P.E. “It is a very attractive and natural-looking fishway, and we’re proud to have created a design that fits so well into the surrounding landscape.”

Princeton Hydro has designed, permitted, and overseen the reconstruction, repair, and removal of a dozens of small and large dams in the Northeast.  To learn more about our fish passage and dam removal engineering services, visit: bit.ly/DamBarrier.

Princeton Hydro Celebrates 20 Years of Science, Engineering, and Design

Princeton Hydro, LLC celebrates two decades of business and
unveils its new look!

Today, Princeton Hydro, LLC is proud to celebrate 20 years since its inception. Princeton Hydro has grown from a small four-person idea operating out of a living room to a 53-person qualified small business with five office locations in the Northeast region. Last year, the firm generated $7.5 million in revenue, as it continues to grow its market share and breadth of ecological and engineering services.

“We are committed to changing the world we live in for the better.  In everything we do, we strive to improve our ecosystem and our quality of life. This firm was originally built upon the ideal of creating a workplace of innovation and passion in the areas of science and engineering,” said Geoffrey Goll, Princeton Hydro’s current President and co-founder. “And, we did not do it alone; the people that were brought aboard helped grow us to what we are today, and will continue to increase our reputation of honesty, integrity, and creativity.”

Two decades ago, Mark Gallagher; Geoffrey Goll, P.E.;  Dr. Stephen Souza; and Dr. Fred Lubnow, along with several staff decided it was time to leave the corporate culture to start a new company focused on the management and restoration of water resources. All four had been employed by a small business named Coastal Environmental Services when it was bought out by the large engineering firm Post Buckley Schuh and Jernigan (PBSJ) in 1996.  None of the “fab four” really fit the “big company” mold, and so the highly regarded wetland scientist, top-notch professional engineer, and well-respected aquatic ecologists formed Princeton Hydro; a company with a mission true to their environmental roots and consistent with their moral compass.

“It’s hard to believe that it has been 20 years since our humble beginning in a small office, a former dance studio lined with mirrors, above a gym in Lambertville. I am proud, yet, still somewhat amazed at how the firm evolved into a well-respected firm of over 50 employees with offices in four states,” stated Mark Gallagher, Vice President and co-founder. “All this from a few important decisions made over breakfast at a Denny’s on Route 1 in 1998 that established a vision for this company. Since that breakfast, we have had the opportunity to implement this vision and to steward the development of Princeton Hydro.”  

After moving from their home office to Lambertville, New Jersey in the same building as the original River Horse Brewing Company location, the company began to grow. At times they struggled to make ends meet, but by supporting each other and celebrating their accomplishments, the team pushed forward. Eventually, they grew so much that they moved down the road to their own office space in Ringoes, and then branched off with offices in southern New Jersey, Eastern Pennsylvania, Connecticut, and Maryland.

The firm and its people have won dozens of awards since its founding; the most recent honor includes the 2018 “Land Ethics Award of Merit” presented by Bowman’s Hill Wildflower Preserve to Princeton Hydro and GreenVest, LLC for their restoration work at the Mullica River Wetland Mitigation Site.

“Over the years we remained true to our goal of doing right by the environment. Princeton Hydro has grown from a humble start-up to a well-recognized and respected leader in the management and restoration of our water, wetlands and natural resources,” said former President and co-founder Dr. Stephen Souza. “Thank you to all that have supported us and have helped us grow. Here’s to another successful 20 years!”

Importantly, it is at this point in the company’s history, the firm’s future is no longer solely dependent on its four founders as its future now relies heavily on the firm’s leadership team and staff to continue the firm’s growth into its next 20 years.  The Princeton Hydro team has the skill sets necessary to conduct highly comprehensive assessments; develop and design appropriate, sustainable solutions; and successfully bring those solutions to fruition. All of our ecological investigations are backed by detailed engineering analyses, and all of our engineering solutions fully account for the ecological and environmental attributes and features of the project site.

“I can’t believe 20 years have passed since the establishment of our firm. This is an absolute testament to Princeton Hydro‘s core principle of bringing together the best, most innovative people to preserve and restore a variety of ecosystems throughout the Mid-Atlantic region,” said Dr. Fred Lubnow, Director of Aquatic Programs and co-founder. “It has been a pleasure to work with Steve, Mark, Geoff and all of the staff at Princeton Hydro over the last 20 years. I’m looking forward to many more!”

As part of Princeton Hydro’s 20th anniversary celebration, the firm unveiled a refreshed brand which includes a new logo, 20th anniversary logo, colors, and style. As we transition into this new look, we’ll be updating our online presence and external communications over the next few months.  This new style matches the evolution of our company since our original “pH” concept was designed in 1998.